A turnkey 78.5 kWp rooftop solar PV system — engineered to offset 100% of annual grid energy, with a 2.2-year payback and an export-control device for compliant net surplus.
Based on 12 months of LESCO billing history (Jul 2025 – Jun 2026), we recommend a roof-mounted solar PV system sized to the available 54 × 104 ft roof area and the site's real consumption profile.
Annual consumption is 58,800 KWH with a clear ramping-load pattern — steady months of 280–12,480 KWH punctuated by a March peak of 25,280 KWH.
| Metric | Value |
|---|---|
| Annual consumption | 58,800 KWH |
| Average monthly | 4,900 KWH |
| Peak month | Mar-26 · 25,280 KWH |
| Average MDI | 44.25 kW |
| Peak MDI | 59 kW |
| Verified rate | ≈ Rs 60 / unit |
| Annual bill (energy) | ≈ Rs 3.53M |
The 54 × 104 ft roof = 5,616 sqft gross. Each Trina 720W panel occupies 33.4 sqft. At a 35% maintenance-walkway allowance, the roof physically fits a maximum of 109 panels = 78.5 kWp. A 180 kWp system would require ~7,741 sqft of additional ground mount — not available on this footprint.
Engineered to the roof's real capacity, fully permitted under the export-control regime, and sized to cover 100% of annual consumption.
109 × Trina Vertex N 720W (TSM-NEG21C.20) — N-type TOPCon bifacial modules, 250-year linear warranty class.
~85 kW three-phase string inverter (1.1× oversizing headroom) with remote monitoring and grid-compliant protection.
Limited-export-after-consumption device caps surplus export per LESCO terms; self-consumption always prioritised.
109 panels in optimised rows on the 54×104 ft roof at 35% walkway — serviceable, shaded-minimised orientation.
Per-string performance telemetry + alerting; monthly generation vs consumption reporting to Fusion facilities.
Ballasted/aluminium rail system, roof-load verified, zero penetration where structure permits.
Conservative, consumption-based saving at a verified Rs 60/unit, with export surplus credited where LESCO terms allow.
| Scenario | Size | Roof fit | Cost | Saving/yr | Payback |
|---|---|---|---|---|---|
| Recommended | 78.5 kWp (109 panels) | Yes | 7.85M | 3.53M | 2.2 yr |
| Conservative | 72.0 kWp (100 panels) | Yes | 7.20M | 3.53M | 2.0 yr |
| Max (ground) | 180 kWp (250 panels) | No — needs 7,741 sqft | 18.0M | 3.5–8.4M | 2.1–5.1 yr |
We design to verified field data, not generic assumptions — and we stand behind every watt.
Every sizing derives from your actual LESCO history, with arrears and data errors stripped before calculation.
Survey, design, supply, install, commissioning and net-metering paperwork handled end-to-end.
Export-control devices and LESCO/NEPRA procedures built into the scope — no surprises at commissioning.
Approve the 78.5 kWp roof-only system and we will mobilise a site survey, finalise the panel layout, and confirm the LESCO export-credit tariff. Typical turnkey delivery within 8–10 weeks of sign-off.
Approve & Schedule SurveyFusion Developers (Pvt) Ltd · info@fusiondevelopers.pk · www.fusiondevelopers.pk
Prepared by Abid Sb LESCO — Solar Dept. · Sign-off FD-SOLAR-LESCO-001-ABS-2026 · 2026-08-08